3E - RESOLUTION AWARDING CONTRACT NO. S-979, PUMP STATION NO. 1 SEAWALL IMPROVEMENTS, TO KEARNS CONSTRUCTION COMPANY IN THE AMOUNT OF $12,558,430.30 AND A TOTAL CONTRACT PERIOD OF 627 CALENDAR DAYS; AUTHORIZING THE COUNTY MAYOR OR COUNTY MAYOR'S DESIGNEE TO UTILIZE THE MIAMI-DADE WATER AND SEWER DEPARTMENT'S CONSENT DECREE AND CAPITAL IMPROVEMENT PROGRAMS ACCELERATION ORDINANCE, SECTION 2-8.2.12 OF THE CODE OF MIAMI-DADE COUNTY, FLORIDA, TO MANAGE THE CONTRACT; AND AUTHORIZING THE COUNTY MAYOR OR COUNTY MAYOR'S DESIGNEE TO EXECUTE THE CONTRACT AND EXERCISE THE TERMINATION AND OTHER PROVISIONS CONTAINED THEREIN(Water & Sewer Department)

October 15, 2026